Factory building construction

Factory building construction include raw ore bin, crushing plant, grinding floating plant, concentrated ore filtering construction, smelting plant, tailings pond, etc.

Facilities construction include water, electric, road construction, civil construction, equipment installation, laboratory construction, etc. Others are water treatment, agentia storage and configuration plant, warehouse, overhaul plant, high water pool, living area facilities construction, etc.

Equipment installation
Equipment transportation

Equipment installation include the installation of crusher, screen, ball mill, classifier, flotation cell, thickener, filter and auxiliary equipment and so on. All the equipment are checked strictly before delivery and guarantee the high-speed, shortcut, non damage. Whatever the stormy weather, deliver goods on time, don't waster customers' time.

Equipment installation

The flow sheet of Equipment installation is : construction checking→ main equipment installation→ platform installation → civil construction→ auxiliary equipment installation→ non-standard parts installation→ electrical equipment installation→ piping installation→ automation installation→ cable line installation→ commissioning in site→ rechecking.

Testing of equipment

Equipment commissioning means checking, running, empty running, test running with water to all equipment, cable line, piping and so on. The purpose of equipment commissioning is check all aspects situation of the equipment. The purpose of process commissioning is re-adjustment of the before optimal process.

Because the mineral processing experiment is done in laboratory, it has some inapplicability in real factory. Jinpeng will arrange the engineers to adjust the process until optimal process and solve the problem occurring when theory become to reality.

EPCM Service